Cal Water Alerts

Installing above-ground main on PV Drive South, near Wayfarers Chapel

Summary: Crews to begin installation of main above-ground beginning March 4.

Current status: Construction completed, and main in service.

Installation of the above-ground water main near Wayfarers Chapel began on Monday, March 4. Crews expect to complete construction the week of March 11, after which we will conduct pressure and water quality testing. After favorable results are received, we will place the new main into service.

UPDATE: Crews have completed construction, conducted pressure and water quality testing, and tied the new main into the system.

Return to Rancho Palos Verdes Community Update Center