Flat to Meter: Marysville

Estimated Schedule

This table shows Cal Water's estimate for installation of water meters in the Marysville district. Meter installations are grouped into "projects" for planning purposes. For each project, a map will be available that shows exactly what locations will be completed during that project (new maps will be added to this page as they become available).

We are currently working on Project 1. If work progresses as planned, we will move to Project 2 in June. Remember that the schedule below is just an estimate; it will be updated as more information becomes available.

Project Date Approximate Boundaries  
1 Complete 715 9th St – 831 G St Map 1PDF Document
2 Sept. 2009 824 Orange St – 631 8th St Map 2PDF Document
2 Sept. 2009 329-1/2 B St – 315 8th St Map 2PDF Document
3 May 1, 2010 1201 G St – 1214 Pine St Map 3PDF Document
4 Sept. 2010 616 12th St – 1010 F St Map 4PDF Document
4 Sept. 2010 1104 Johnson Ave – 1230 Val Dr Map 4PDF Document
5 May 1, 2011 1261 Gavin Dr – 2434 Hall St Map 5PDF Document
6 Sept. 2011 2205 Jean Dr – 1378 Johnson Map 6PDF Document
7 May 1, 2012 1303 Sicard St – 1310 Sicard St Map 7PDF Document
8 Sept. 2012 512 E 14th – 505 E 15th St Map 8PDF Document
9 May 1, 2013 1215 Ramirez St – 1329 Swezy Map 9PDF Document
10 Sept. 2013 1501 Sampson St – 4 14th St Map 10PDF Document
11 May 1, 2014 416 12th St – 505 Washington Sq Map 11PDF Document
12 Sept. 2014 1114 E 19th St – 1115 E 22nd St Map 12PDF Document
13 May 1, 2015 1940 Hall St – 1710 Hall St Map 13PDF Document
14 Sept. 2015 1041 E 17th St – 1706 Huston Map 14PDF Document
14 Sept. 2015 222 E 17th – 1812 Buchanan Map 14PDF Document
15 May 1, 2016 1811 Ramirez – 1806 Sampson Map 15PDF Document
16 Sept. 2016 229 E 24th St – 4 Triplett Way Map 16PDF Document
17 May 1, 2017 432 E 25th – 633 E 22nd St Map 17PDF Document
18 Sept. 2017 634 E 24th St – 2457 Del Pero St Map 18PDF Document
19 May 1, 2018 721 E 24th St – 2204 Buchanan Map 19PDF Document